Water and Finance | Jordan Invests $6.7 Billion to Bring Desalinated Red Sea Water to Amman

Construction on the Aqaba–Amman desalination and water conveyance project began on November 18, 2026. Led by Meridiam alongside SUEZ and its partners, the project is designed to produce more than 300 million cubic metres of drinking water a year and carry it nearly 418 kilometres to the Jordanian capital. Pumping is scheduled to begin by the end of 2030, and the project could meet around 40% of the kingdom’s drinking water needs.

In Jordan, many families organise their lives around the water supply schedule. Most households have access to running water for fewer than two consecutive days a week. To ease this chronic shortage, Jordan is building a plant on the Gulf of Aqaba to desalinate seawater and pump it inland to Amman.

On November 18, Prince Faisal bin Al Hussein laid the foundation stone on behalf of King Abdullah II. The following day, during the Jordan–European Union Investment Conference, the Jordanian government and Meridiam signed a $6.6 billion agreement to move the project into construction. Total investment is estimated at $6.7 billion.

From the Red Sea to Amman, the challenge of pumping water uphill

The Aqaba plant will have a design capacity of 851,000 cubic metres a day. A pipeline stretching nearly 418 kilometres will carry the treated water to the capital. Pumping stations along the route will lift it to approximately 1,100 metres above sea level, making electricity for pumping a major factor in the cost of each cubic metre delivered.

Jordanian authorities estimate that the project could raise annual water availability from 60 to 110 cubic metres per person and increase supply across the governorates from one day to three days a week. For households, the improvement will also depend on how reliably local networks can distribute the additional water.

A 30-year concession backed by public and private capital

The project is structured as a 30-year public-private partnership. The Meridiam-led consortium brings together SUEZ, Jordan’s Social Security Investment Fund, VINCI Construction Grands Projets and Egypt’s Orascom Construction, among others. SUEZ and Orascom will jointly design and build the desalination plant, then operate it and the water conveyance system.

The financing combines equity, international and local-currency borrowing, and grants. The European Investment Bank announced a $400 million loan backed by an EU guarantee, alongside an existing €300 million sovereign loan. The package also includes a €97 million EU grant and a €30 million Dutch grant. These commitments spread the financing across the project company, the Jordanian government and its international partners.

Solar power will cover around 30% of the project’s energy needs

A dedicated 280-megawatt solar plant is planned to reduce reliance on grid electricity. Its output is expected to cover the equivalent of around 80% of the desalination plant’s energy needs and 30% of the entire project’s needs, including pumping and transport. The gap between those figures shows how much energy it takes to move water from the Red Sea coast to Amman.

Once the project is operational, its success will depend on keeping the water supply reliable and the cost of delivering it under control. That will require maintaining the pumping stations and hundreds of kilometres of pipeline throughout the concession. For households accustomed to rationing, the clearest measure of that investment will be how many more days a week water comes out of the tap.